10-06-2024 | Notification S.R.O No. 845(I)/2024 - NEPRA hereby notifies the Determination of the Authority dated 7th February, 2024 in the matter of Decision of Appellate Tribunal regarding Modification of Fuel Price Mechanism of Bagasse Based Power Projects | View |
10-06-2024 | Decision of the Authority in the matter of Reconsideration request of the Federal Government U/S 31(7) of the NEPRA Act, 1997 read-with all enabling Provisions with respect to the Determination of the Authority in the matter of Decision of Appellate Tribunal regarding modification of Fuel Price Mechanism of Bagasse-Based Power Projects | View |
07-02-2024 | Determination of the Authority in the matter of Decision of Appellate Tribunal regarding Modification of Fuel Price Mechanism of Bagasse based power projects | View |
30-09-2020 |
||
Decision of National Electric Power
Regulatory Authority in the Matter of
Motion for Leave for Review Filed by JDW
Sugar Mills Limited against the
Determination of the Authority Dated
November 10, 2017 in the Matter of
Bagasse Upfront Tariff, 2017 for New
Bagasse Cogeneration Power Projects |
||
16-07-2019 |
||
Decision of National
Electric Power Regulatory Authority in the matter of
Suo Moto Review Proceedings regarding
Modification of Fuel Price Mechanism of
Bagasse Based Power Projects |
||
18-04-2018
|
Decision of
National Electric Power Regulatory Authority in the matter of
Review Motions filed by Central Power Purchasing Agency
Guarantee Ltd. against the Award of Upfront Tariff, 2013 to
Twelve Bagasse Cogeneration Projects |
|
10-11-2017 |
Determination of the
Authority regarding Upfront Tariff 2017 for New Bagasse
Based Cogeneration Power Projects |
|
31-10-2016 |
Corrigendum - Decision
of the Authority in the matter of Adjustment of Upfront Tariff for
New Bagasse Based Co-generation Projects dated July 7, 2015
|
|
07-07-2015 |
Decision of the Authority in the matter
of Adjustment of Upfront Tariff for New Bagasse Based
Co-generation Projects |
|
17-06-2015 |
Decision of the Authority in the matter
of Upfront Tariff for New Bagasse Based Co-generation Projects
- Extension for Date of Acceptance of Upfront Tariff |
|
19-06-2014 |
Decision of the Authority in the matter of Upfront Tariff for New
Bagasse Based Co-generation Projects — Extension for Date of
Acceptance of Upfront Tariff |
|
28-08-2013 |
Decision of the Authority in the matter
of Suo Moto Action for Modification of Existing Terms and
Conditions: of Upfront Tariff for New Bagasse Based Cogeneration
Power Projects |
|
29-05-2013 |
Determination of the Authority in the matter of Suo-Moto Proceedings
for Development of Upfront Tariff for New
Bagasse Based Co-Generation Power Projects |
15-12-2017 |
Determination of the Authority in the matter of
Upfront Generation Tariff for Biomass Power Projects |
23-09-2016 |
Decision of the Authority regarding Suo
Moto Review Proceedings in the Fuel Price Adjustment Mechanism
Determined in Upfront Coal Tariff |
|
19-09-2016 |
Decision of the
Authority regarding Cessation of Upfront Tariff on Imported/Local
Coal |
|
11-08-2016 |
Decision of the
Authority in the matter of Motion for Leave for Review against the
Decision of the Authority regarding Reconsideration Request filed by
Government of Pakistan in the matter of Upfront Tariff for Coal
Power Projects |
|
02-07-2015 |
Corrigendum - Decision of the
Authority in the matter of Upfront Generation Tariff for
Imported/Local Coal Power Plants dated 26.06.2104 |
|
21-11-2014 |
Decision
of the Authority in the matter of Review Petition filed by Fazal-e-Akbar
& Company on behalf of Asad Umer (Member National Assembly) under NEPRA (Review Procedure) Regulations 2009 with respect to the
Upfront Tariff of Coal dated 26.06.2014 |
|
26-06-2014 |
Decision of the Authority
regarding Reconsideration Request filed by Government of Pakistan in
the matter of Upfront Tariff for Coal Power Projects |
|
29-10-2013 |
Draft Standardized
Coal Supply Agreement
provided by Punjab Mineral Company
|
|
04-09-2013 |
Notification in respect of NEPRA, Upfront
Tariff for the project of imported/local coal |
|
06-06-2013 |
Summary of Upfront Coal Tariff |
|
Announcement of Upfront Coal Tariff | ||
11-01-2008 |
Indicative Tariff for COAL based
Power Plants |
27-07-2017 |
Determination of the
Authority in the Matter of Upfront Generation Tariff for the
Projects on Thar Coal |
|
18-01-2017 |
Decision of the
Authority regarding Cessation of Thar Coal Upfront Tariff |
|
10-11-2014 |
Corrigendum —
Determination of the Authority in the matter of Thar Coal Upfront
Tariff |
|
09-07-2014 |
Determination of the
Authority in the Matter of Thar Coal Upfront Tariff |
16-01-2018 |
Decision of the Authority in the matter of
Review Motion filed against Authority's Decision dated 28th July 2017
in the matter of Upfront Tariff for Captive Power Plants on RFO for Short
Term Utilization of the Available Generation Capacity |
|
28-07-2017 |
Determination of the Authority in the matter of
Upfront Tariff for Captive Power Plants on RFO for Short Term Utilization
of the Available Generation Capacity |
31-07-2017 |
Determination of the Authority in the Matter of Upfront Tariff for Captive Power Plants on Coal for Short Term Utilization of the Available Generation Capacity |
16-01-2018 |
Decision of the Authority in the matter of
Review Motions filed against Authority's Decision dated 31st July
2017 in the matter of Upfront Tariff for Captive Power Plants on Gas for
Short Term Utilization of the Available Generation Capacity |
|
31-07-2017 |
Determination of the Authority in the Matter of
Upfront Tariff for Captive Power Plants on Gas for Short Term Utilization of
the Available Generation Capacity |
10-04-2017 |
Decision of the Authority in the matter of Upfront
Tariff for Small Hydro Power Generation Projects up to 25 MW
Installed Capacity — Extension of Date of Acceptance of Upfront
Tariff |
|
14-10-2015 |
Decision of the National Electric Power
Regulatory Authority in the matter of Motions for Leave for
Review filed against Determination of the Authority dated April
2, 2015 regarding Upfront Tariff for Small Hydro Power Generation
Projects Upto 25 MW Installed Capacity |
|
02-04-2015 |
Determination of National Electric Power Regulatory Authority in the
Matter of Upfront Tariff for Small Hydro Power Generation
Projects Upto 25 MW Installed Capacity |
|
14-02-2013 |
Decision of the Authority in the matter
of Petition filed by Punjab Power Development Board (PPDB) for Approval of Upfront Tariff for
Small Hydropower
Projects in Punjab |
10-07-2018 |
Decision of the
Authority in Suo Moto Review Proceedings of
the Upfront Tariff Determination Dated
January 15, 2018 for Municipal Solid Waste Power
Projects |
View |
15-01-2018 |
Determination of the Authority in the Matter of
Upfront Generation Tariff for Municipal Solid Waste Power
Projects |
View |
09-02-2016 |
Decision of the Authority in the Matter
of Motions for Leave for Review filed against the Determination of
the Authority dated 03.04.2015 regarding Upfront Generation
Tariff for RLNG Based Power Plants |
|
03-04-2015 |
Determination of the
Authority in the Matter of Upfront Tariff for RLNG Based
Power Plants |
20-09-2017 |
||
Decision of the National
Electric Power Regulatory Authority in the matter of Motion for
Leave for Review filed against Decision of the Authority dated March
3, 2017 in the matter of Solar PV Power Generation Tariff |
||
18-07-2018 |
Decision of the
Authority in the matter of Suo Moto Review
Proceedings regarding Adjustment of Tariff of
Renewable Energy Power Projects availing
State Bank of Pakistan Revised Financing Scheme |
|
03-03-2017 |
Decision of Authority in the Matter of Solar PV Power Generation Tariff |
|
19-04-2016 |
Decision of the
Authority in the matter of Motions for Leave for Review in the
matter of Upfront Solar PV Tariff dated 16.12.2015 |
|
16-12-2015 |
Determination of National Electric Power Regulatory
Authority in the Matter of Upfront Generation Tariff
for Solar
PV Power Plants
|
|
Notification S.R.O: 1243 | ||
25-05-2015 |
Decision of the
Authority in the Matter of Motion for
Leave for Review filed against the
Determination of the Authority dated
22.01.2015 regarding Upfront Generation
Tariff for Solar PV Power Plants |
|
20-02-2015 |
Corrigendum - Determination of the Authority in
the Matter of Upfront Generation Tariff for Solar PV Power Plants
Dated 22.01.2015 |
|
22-01-2015 |
Determination of
National Electric Power Regulatory Authority in the Matter of
Upfront Generation Tariff for Solar PV Power Plants |
|
05-12-2014 |
Decision of the
Authority in the matter of Extension in Date of Financial Close for
Solar Power Projects under Upfront Solar Tariff |
|
26-02-2014 |
Corrigendum -
Decision of the Authority in the matter of
Upfront Tariff for Solar PV Power Plant |
|
21-01-2014 |
Determination of
National Electric Power Regulatory Authority in the Matter of
Upfront Tariff for Solar Power Plants |
07-04-2015
|
Determination of the Authority in the
matter of Utilization of Existing Available Generation Capacity
Policy for Short Term Independent Power Producers (STIPPs) |
04-01-2007 | Decision of the Authority w.r.t. Extension of Validity Date of Upfront Tariff for IPPs | View |
19-12-2006 | Decision of the Authority w.r.t. Adjustment Formula for Calculation of Tariff for Old/Refurbished Plants of Reciprocating Engines Technology | View |
14-09-2006 | Revised Upfront Tariff for Reciprocating Engines Technology | View |
13-03-2006
|
Upfront Tariff for New Independent Power
Producers |
10-05-2017
|
Decision of the Authority in the matter of Suo
Moto Proceedings for Development of Upfront Tariff for Waste Heat
Recovery Power Projects |
18-07-2018 |
Decision of the
Authority in the matter of Suo Moto Review
Proceedings regarding Adjustment of Tariff of
Renewable Energy Power Projects availing
State Bank of Pakistan Revised Financing Scheme |
|
30-05-2017 |
Decision of the National Electric Power Regulatory
Authority in the matter of Review Motion filed by Government of
Sindh against the Determination of New Tariff for Wind Power
Generation Projects |
|
27-01-2017 |
Determination of New Tariff for
Wind Power Generation Projects. |
|
24-06-2015 |
Determination of
National Electric Power Regulatory Authority in the Matter of
Upfront Tariff for Wind Power Generation |
|
19-10-2015 |
Decision of the
Authority in the Matter of Motions for Leave for Review filed
against the Determination of the Authority dated June 24, 2015 in
the matter of Upfront Tariff for Wind Power Plants |
|
02-05-2014 |
Decision of the
National Electric Power Regulatory Authority in the matter of
Review of Determination of Upfront Tariff for Wind Power Generation |
|
06-08-2013 |
Decision of the Authority in the Matter
of Motion for Leave for Review Filed by NBT Wind Power Pakistan
(Pvt.) Limited Against Determination of Upfront Tariff for Wind
Power Generation - Intimation of Decision of Tariff pursuant to
Section 31 (4) of the Regulation of Generation, Transmission and
Distribution of Electric Power Act (XL of 1997) |
|
24-04-2013 |
Determination of National Electric
Power Regulatory Authority in the Matter of
Upfront Tariff for Wind Power Generation |
|
06-10-2011 |
Determination of
National Electric Power Regulatory Authority (NEPRA) in the matter
of Upfront Tariff for Wind Power Projects
|
|
07-02-2007 |
Revised Upfront Tariff for Wind Power Generation | View |
06-02-2007 |
Revised Upfront Tariff for Wind Power Generation | View |
17-01-2007 |
Revised Upfront Tariff for Wind Power Generation Plants | View |
12-09-2006 |
Upfront Tariff for Wind Power Generation without Assumption | |
28-04-2006 |
Upfront Tariff for Wind Power Plants | View |